The Jamalco Alumina Refinery at Halse Hall utilizes a temporary platform in facilitating the operations and maintenance team with access to a section of the new 12” (300mm) steam line instrumentation. As it stands, the temporary platform (scaffolding) presents safety and work efficiency concerns for the instrumentation team and requires a permanent fixture In facilitating the requests of the client.
CEAC Solution was engaged to provide a proposal for the engineering designs of a fixed working platform for the Instrumentation Loop access. It is proposed that the proposed working platform be connected to and accessed via the existing C17 tank platform.